一、编制依据 ·················································································· 2 二、工程概况 ·················································································· 2 三、土方开挖方案 ············································································ 3 (一)、开挖准备 ·············································································· 3 1、基坑周边及基坑内排水措施 ······················································· 3 2、基坑测量定位 ········································································· 3 3、施工人员及材料设备的准备 ······················································· 3 4、施工用电及施工照明的准备 ······················································· 4 (二)、基坑开挖的原则、顺序和方法 ··················································· 4 (三)、主要机械设备计划 ·································································· 4 (四)、主要施工方法与要求 ······························································· 5 1、技术措施 ··············································································· 5 2、基槽验收 ··············································································· 6 四、土方回填方案 ············································································ 6 1、 土料要求与含水量控制 ···························································· 6 2、基底处理 ··············································································· 7 3、 压实的一般要求 ····································································· 7 4、质量控制与检验 ······································································ 8 五、工期与工期保障措施 ··································································· 8 六、土方坍塌应急预案 ····································································· 10 1、现场可能发生坍塌事故的环节···················································· 10 2、预防措施 ·············································································· 10 3、应急预案工作流程图 ······························································· 10 4、基坑安全处理措施 ·································································· 11 七、安全管理 ················································································· 11 八、文明施工 ················································································· 12
1
土方开挖与回填土施工方案
一、编 制 依 据
1、××××××××工程《施工组织设计》; 2、××××××××工程施工总平面布置图; 3、××××××××工程设计文件;
4、××××××××工程《地质勘察报告书》; 5、《建筑工程质量验文件收统一标准》(GB50300-2001); 6、《建筑地基基础施工质量验收规范》(GB50202-2002); 7、《建筑施工安全检查标准》(JGJ59-1999); 8、《施工现场临时用电安全技术规范》(JGJ46-2005); 9、《建筑机械使用安全技术规范》(JGJ33-2002);
二、工 程 概 况
××工程位于××省××市××区××镇,工程由××设计研究院有限公司设计,××市地质勘探院地质勘察,××省建设监理有限公司监理,××公司总承包。
本工程±0.000m,相当于黄海高程20.5m。工程总建筑面积11700㎡,建筑基底面积7900㎡,钢筋砼基础,柱网为9*9m,建筑总高度为21.15m。
基础开挖基底相对标高分别为-2.6m;-3.1m; -4.6m;-5.1m等,实际开挖深度分别为2.3m;2.8m;4.3m;4.8m等。根据地质勘察报告及施工场地比较开阔,无障碍物,便于施工布置的特点。基础采用机械大开挖分层作业施工的方法人工清底的预留厚度为300㎜,土方开挖量22000m3,开挖出的土方在施工区附近集中堆放,基础回填结束后剩下的土方,全部外运出机场区域。
2
三、土方开挖方案
(一)、开挖准备
本工程地基与基础施工阶段,在当地正处于雨期季节,做好土方开挖前期各项准备工作至关重要,也十分必要。 1、基坑周边及基坑内排水措施
为防止基坑上部的地表、地面的水流入基坑内,基坑周边要做好组织排水。
(1)、离基坑上口50-80cm处设40cm高、60cm宽排水沟(必要时用砌筑),与硬化地面连接,形成封闭状态。
(2)、为确保雨期基槽不被雨水浸泡,需在基槽内每18M(离开承台位置)设600*600大小、挖深800mm的集水井(具体数量和布局可视天气情况而定),将基槽内雨水利用明排方法排至集水井内,并用污水泵及时强排至场外。
(3)、雨施期间,安排专人观测水位情况,特别是在中、大雨过后,如发现水位异常上升时需采取措施加强降水。 2、基坑测量定位
根据施工图纸及轴线控制点进行测量放线,挖土时不允许超线开挖。基坑开挖前先进行测量定位,抄平放线,确定基坑平面尺寸和每个承台的外围线。根据本工程的±0.000标高原点,边挖土边测标高,直至挖到设计要求高度。
3、施工人员及材料设备的准备
施工现场管理人员及各岗位操作人员均应到位,对作业人员进行详细的书面技术交底,项目管理技术人员、现场各专业负责人必须吃透施工图纸领会施工方案的各项要求和工艺技术标准,并向所有施工人员进行交底。基坑开挖时所有材料及应急材料按计划全部到位。
3
4、施工用电及施工照明的准备
利用晴好天气采取连续施工作业方法,夜间挖土工作时间长,为保证充分的施工照明,拟在场地内搭设六只高度为4m~6m的照明灯架,每个灯架安装功率2000kw镝灯,工作面处配置15只活动碘钨灯。
(二)、基坑开挖的原则、顺序和方法
1、开挖原则。根据本工程柱网密、基础深、基底标高不一致的特点,基坑开挖必须坚持遵守“分段施工、分层开挖、先中间后周围、成半岛形开挖”的原则。
2、开挖顺序。基坑开挖顺序由西向东,从拟建工程的○10-○11轴间(后浇带)分开,第一施工段为 ○1-○10轴;第二施工段为○11-○17轴。用三台挖掘机同时开挖(一台配合施工);一台在中间○B-○C轴先行作业,要有一定的安全作业空间后,南、北两台即可开挖作业,形成既分散开挖、又整体推进施工作业流程。
3、开挖方法。基坑土方开挖采用分层、分块、对称、限时和严禁超挖的方法进行。○A轴分别按2.8m、4.3m、4.8m、5.3m的深度分层进行开挖。其他基坑均按2.3m的深度一次性开挖到位的方法进行。中间○B-○C轴挖出的土用自卸运输车运出场地,南、北两边的土就随即甩至坑外装载机、挖掘机配合疏散。
(三)、主要机械设备计划
4
本工程计划投入如下机械、设备(材料)
序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 名 称 全站仪 经纬仪 水准仪 塔 尺 反铲挖掘机 推土机 装载机 自卸运输车 压路机 抽水泵 防水彩条布 钢 管 手推车 铁 锹 蛙式打夯机 平板振动夯 规 格 NTS302 J6 S3 5m 1m3 DC140 ZT50 康明斯25T 15T带震动 扬程50m φ48 ZH85 单 位 台 台 台 根 辆 辆 辆 辆 辆 台 ㎡ m 辆 把 台 台 数 量 1 1 2 2 4 1 2 6 1 10 4000 1500 10 40 4 2
(四)、主要施工方法与要求
根据本工程特点,基坑采用机械大开挖,按两个施工段、分层施工的方法整体推进。必须严格按照其放坡的灰线进行开挖,。由3台反铲挖掘机从西①轴向东○17轴开挖,6辆运输车运土,1台挖掘机和1台推土机负责转运堆土和修坡,1台装载机和1台压路机配合修路。 1、技术措施
(1)、施工前由现场负责人向所有参加施工的人员进行有针对性的技术
5
交底,必须使每个操作者对施工中的技术要求心中有数。管理人员要了解施工机械设备的技术参数与性能,做好维修保养,科学合理地安排施工,尽量做到24小时人歇机械不歇。
(2)、基底标高的控制。当土方开挖快接近基底标高时,在边坡上用钢筋并撒上白灰作出基底标高控制线,使槽底预留达到20cm土方,其中10cm土方用人工进行开挖,最后保留的10cm土层,待钎探进行后再用人工清槽。
(3)充分发挥集水坑的效能。严格按设计方案布控集水坑,切实做好防水布(薄膜)的遮盖工作,严防基坑浸泡或爆晒。现场排水时采用电动潜水泵及时将集水坑的水排除场外。整个地基与基础施工过程派专人进行值班,确保施工正常进行。 2、基槽验收
人工清理基槽到设计标高时,及时通知设计单位、地质勘察单位、建设单位、监理单位进行基槽验收。验收内容:地质情况,基槽验线、尺寸、标高、基底地质情况。同时签署有关资料文件,合格后,才能进行下一道工序施工。
四、土方回填方案
本工程基础下采用褥垫渣褥垫。基础持力层为3层粉质粘土夹砾石和4层砂砾岩为基础持力层,如遇岩石地段开挖高度为基础埋深加300,采用褥垫渣褥垫。处理回填措施,褥垫层每次虚铺厚度可取300 mm。褥垫材料采用炉渣施工时,严格控制夯填度,炉渣取0.65。 1、 土料要求与含水量控制
填方土料应符合设计要求,应选择含水量符合压实要求的土作为填料,保证填方的强度和稳定性。填土土料含水量的大小,直接影响到夯实(碾压)质量,在夯实(碾压)前应先试验,以得到符合密实度要求条件下的最优含水量和最少夯实(或碾压)遍数。含水量过小,夯压(碾压)不实;
6
含水量过大,则易成橡皮土。粘性土料施工含水量与最优含水量之差可控制在-4%~+2%范围内(使用振动碾时,可控制在-6%~+2%范围内)。
土料含水量一般以手握成团,落地开花为适宜。当含水量过大,应采取翻松、晾干、风干、换土回填、掺入干土或其他吸水性材料等措施;如土料过干,则应预先洒水润湿。 2、基底处理
(1)、场地回填应先清除基底上垃圾、草皮、树根,排除坑穴中积水、淤泥和杂物,并应采取措施防止地表滞水流入填方区,浸泡地基,造成基土下陷。
(2)、当填方基底为耕植土或松土时,应将基底充分夯实和碾压密实。 3、 压实的一般要求
(1)、密实度要求。填方的密实度要求和质量指标通常以压实系数λc表示。压实系数为土的控制(实际)干土密度ρd与最大干土密度ρdmax的比值。最大干土密度ρdmax是当最优含水量时,通过标准的击实方法确定的。
(2)、铺土厚度和速度。选用重型15t振动压路机,每层铺土厚度为250~300mm。为保证填土压实的均匀性及密实度,避免碾轮下陷,提高碾压效率,在碾压机械碾压之前,先用装载机使表面平实,应先静压,而后振压。行驶速度不超过2km/h,并要控制压实遍数。
(3)、碾压方向。碾压方向应从两边逐渐压向中间,碾轮每次重叠宽度约15—25cm,避免漏压。运行中碾轮边距填方边缘应大于500mm,以防发生溜坡倾倒。边角、边坡边缘压实不到之处,应辅以人力夯或小型夯实机具夯实。压实密实度,除另有规定外,应压至轮子下沉量不超过1~2cm为度。碾压一层完后,应用人工或推土机将表面拉毛。土层表面太干时,应
7
洒水湿润后,继续回填,以保证上、下层接合良好。 4、质量控制与检验
(1)、填土施工过程中应检查排水措施,每层填筑厚度、含水量控制和压实程序。
(2)、对有密实度要求的填方,在夯实或压实之后,要对每层回填土的质量进行检验,一般采用环刀法(或灌砂法)取样测定土的干密度,求出土的密实度,或用小轻便触探仪直接通过锤击数来检验干密度和密实度,符合设计要求后,才能填筑上层。 (3)、基坑填土,每层按100~500m2取样1组;取样部位在每层压实后的下半部。用灌砂法取样应为每层压实后的全部深度。
(4)、填土压实后的干密度应有90%以上符合设计要求,其余10%的最低值与设计值之差,不得大于0.08t/m3,且不应集中。 (5)、填方施工结束后应检查标高、边坡坡度、压实程度等。
五、工期与工期保障措施
1、工期:施工45日历天。自2010年9月25日---2010年11月9日。 2、工作内容:土方开挖、土方回填至室外标高。
3、管理目标:同项目管理目标,各分项目标责任制必须与总目标一致。 4、劳动力投入:计划投入70人。(木工:20人;钢筋工:20人;泥工:20人;零工:10人)。
5、管理人员分工与主要职责。见下表:
8
管理人员分工与主要职责
序号 姓 名 1 2 3 4 5 6 7 8 9 10 11 6、工期保障措施
(1)、思想重视、措施具体、管理到位。要向全体施管人员进行教育、宣讲基础工程在房屋建筑工程的极端重要性,基础决定建筑;要组织有关人员反复研讨实施方案,并能不折不扣地贯彻执行;各级管理人员必须跟班作业指导,要建立更加严格的检查和考评制度,赏罚分明。
(2)、机械设备始终保持良好的技术状态,应急物资准备充分,布置合理。
(3)、科学组织劳动力、合理安排工序,做好施工技术、安全管理交底,充分调动和发挥工人的积极性、创造性,不断提高施工效益。
(4)、把安全防事故、文明施工放在十分重要的位置,重点抓好塌方、机械伤人、触电等方面的预防工作,常抓不懈。摆正安全工作与工程质量、施工进度的关系,三者必须兼顾,目的必须达到。
职 务 主 要 职 责 ××× 项目经理 全面负责施工管理 ××× ××× ××× ××× ××× ××× ××× 副经理 副经理 施工员 材料员 安全员 试验员 资料员 组织调度施工物质及供应 施工组织与现场管理 生产组织、计划及生产调度、测量验线 落实施工器材计划、材料设备组织及管理 检查督促安全文明施工、安全资料整理 后勤保障及试验取、送样 施工资料的整编 ××× 保卫消防 现场安保卫生及消防工作 ××× ××× 电 工 排水工 施工、生活安全用电及服务保障 检查、巡视排水系统,负责排水措施的实施 9
(5)、做好施工计划,力求一个“早”字。凡事预则立,不预则废,工作要早计划、早安排、早实施,努力提高工作的预见性,才能收到工作的实效。
六、土方坍塌应急预案
1、现场可能发生坍塌事故的环节
(1)、土方施工采用挖空底脚的方法挖土;
(2)、积土、料具、机械设备堆放离坑、槽小于设计规定; (3)、坑槽开挖设置安全边坡不符合安全要求;
(4)、深基坑末设专项支护措施、不设上下通道,人员上下坑槽踩踏边坡;(5)、料具堆放过于集中,荷载过大; (6)、模板支撑系统未经设计计算; (7)、基坑施工未设置有效排水系统等。 2、预防措施
(1)、严禁采用挖空脚底的方法进行土方施工。
(2)、对基坑、井坑的边坡和固壁支架应随时检查,发现边坡有裂痕、疏松或支撑有折断、走动等危险征兆,应立即采取措施,消除隐患。对于挖出的泥土,要按规定放置,不得随意沿围墙(档)或临时建筑堆放。 (3)、基坑施工要设置有效的排水措施,雨天要防止地表水冲刷土壁边坡,造成土方坍塌。 3、应急预案工作流程图
根据本工程的特点及施工工艺的实际情况,认真组织了对危险源和环境因素的识别与评价,特制定本项目发生紧急情况或事故的应急措施,开展应急知识教育,提高现场操作人员应急能力,减少突发事件造成的损害和不良环境影响。其应急准备和响应工作程序见下图:
10
组建抢险队、救护车
配备应急物资、设备 未发生 发生 定期评审 应急知识教育培训
应急准备和响应工作程图 4、基坑安全处理措施
(1)、基坑开挖过程中,设专人进行巡视检查,当发现桩顶水平位移过大,或位移发展速度过快时,应将桩后的土体部分挖除以卸载,并严禁再次对桩后施加其他附加荷载;同时在桩的内侧培土或堆砂袋以增加桩的被动侧土抗力,可以缓解险情的发展,为抢险争取时间,可以有效控制位移的发展。
(2)、当基坑坑底隆起过大时,采用石子草袋增加上部荷载;基坑开挖至坑底标高后应尽快浇筑垫层,使坑底土层封闭,防止坑底土上隆。
(3)、有效发挥坑内集水井及排水明沟,增设水泵数量进行强排水,防止雨水浸泡基坑。
(4)、基坑开挖和使用过程中应控制坡顶的堆载不得超过设计所允许的10kPa。
实施应急预案 进行评审、修订 成立抢险领导小组 危险源及环境因素辨别、评价 编制应急方案 七、安全管理
1、在土方施工阶段,边坡的防塌是难点,除要有科学的计算依据,良
11
好的施工质量外,还应排专人进行基坑监测。出现不良现象及时处理防止出现坍塌事故。
2、边坡开挖工程中,要时刻注意边坡的稳定性,在雨后要仔细观察土壤情况,如发现有裂缝、鼓包、滑动等现象,要及时排除险情后方可施工。
3、基坑周围1m范围内禁止堆放重物。
4、基坑周边搭设防护栏(单排),1.2m高,刷黄黑相间警告漆。 5、现场应保持足够的照明。现场电气设备均作漏电保护装置,配电线采用三相五线制。
6、加强对施工人员的安全教育,做好技术交底和安全交底。 7、当配合机械作业的清底需进入机械旋转半径内时,必须停止旋转,机上和机下人员应密切配合。
8、施工现场应配备大型的照明设备以供夜间挖土施工使用,电工与施工人员同时上下班,确保照明设备安全使用。
八、文明施工
1、所有施工人员应保持现场卫生,垃圾集中堆放,随时清运。 2、合理进行施工现场的平面布置,做到计划用料,使现场材料堆放降低到最低值,保持场内道路畅通。
3、运输散装材料时,车厢应封闭,避免洒落。
4、机械设备完好,安全装置齐全有效,做到专人管理。施工材料堆放整齐。
5、施工区域或危险区域有醒目的安全警示标志,并定期组织专人检查。
×××设总公司 ×××建设工程项目部 二0一0年九月十六日
12
因篇幅问题不能全部显示,请点此查看更多更全内容
Copyright © 2019- pqdy.cn 版权所有 赣ICP备2024042791号-6
违法及侵权请联系:TEL:199 1889 7713 E-MAIL:2724546146@qq.com
本站由北京市万商天勤律师事务所王兴未律师提供法律服务